Bedok South MRT station opens for passenger service on Saturday 26 December 2026, together with Sungei Bedok and Xilin, the Land Transport Authority (LTA) announced on 4 November 2026. For anyone weighing a new home in the east, Bedok South matters most: the Urban Redevelopment Authority (URA) sold the Bayshore Drive Government Land Sales (GLS) site on 20 July 2026 for S$2.128 billion, and URA says the development there will be integrated with Bedok South MRT station, a bus interchange and retail spaces, with about 1,280 homes.
The station opening is the dated, confirmed part. The homes, shops and bus interchange at Bayshore Drive are not built, and as at 20 November 2026 no project name, price or launch date for the site appeared on any official page we could open. General information, not financial advice.
At a glance
- 23 June 2024: the Thomson-East Coast Line (TEL) reached Bayshore station in its fourth stage, according to LTA's Thomson-East Coast Line page.
- 30 March 2026: URA launched the Bayshore Drive tender, a commercial and residential site that "can potentially yield 1,280 residential units".
- 20 July 2026: URA awarded Bayshore Drive to Gemini Residential Pte. Ltd. and Gemini Trustee Pte. Ltd. (as trustee-manager of Gemini Mall Trust) for S$2,128,000,000 on a 99-year lease.
- 4 November 2026: LTA announced the opening date for TEL Stage 5 and the Downtown Line 3 Extension (DTL3e).
- 26 December 2026: TE30 Bedok South, the TE31/DT37 Sungei Bedok interchange and DT36 Xilin open, adding 4.3 km of line. LTA says this completes the TEL's five planned stages, with 29 operational stations over 42.8 km.
Which stations open on 26 December, and what do they connect?
On the TEL, Bedok South and Sungei Bedok extend the line beyond Bayshore, which has been its eastern end since June 2024. Sungei Bedok is also an interchange with the Downtown Line (DTL), whose new Xilin station opens the same day. LTA says the stations improve access to Changi Business Park and Tampines Regional Centre, and that the Sungei Bedok interchange lets passengers transfer between the two lines.
LTA says more than 240,000 households will then be within a 10-minute walk of a TEL station, and over 220,000 within a 10-minute walk of a DTL station. Those are network totals, not a promise about any particular condominium.
URA's Master Plan 2025 page for the East (last updated 2 June 2026) already expected the three stations to open in 2026. Cross Island Line Phase 1, due by 2030 in the same plan, is a separate and later project that URA says will cut travel times for Pasir Ris and Tampines North residents.
How much time will the new stations save?
LTA's release gives two examples in its text (its Annex B of time-savings examples could not be opened):
- Havelock to Changi Business Park: about 45 minutes using the TEL and DTL, saving up to 25 minutes on today's 70.
- Marine Parade to Tampines: time savings of up to 10 minutes compared with today.
An illustrative case: someone commuting from near Havelock station to Changi Business Park five days a week would save up to 50 minutes a day on LTA's figures if the return trip saves as much as the outward one (LTA quotes one direction), or up to 250 minutes, a little over four hours, a week. That is our arithmetic on LTA's example route only, not an LTA figure; a home near Bedok South with a job in Raffles Place, or a school run to Tampines, needs its own timing.
The practical step is to time your actual journeys once the stations are running. Our commute test sets out how: door to door, on a weekday at the hours you would really travel, from the exit nearest the address you are considering.
What is confirmed about the Bayshore Drive site?
URA's releases and its current GLS sites page (last updated 17 November 2026, a change that concerned another site) give these facts:
- Use and size: commercial and residential, site area 57,460.6 square metres (listed as 5.74 ha), gross plot ratio 2.6, maximum gross floor area (GFA) 149,398 square metres.
- Homes: URA's estimate is about 1,280 residential units, part of the 4,575 homes on the first half 2026 Confirmed List. No final unit count appeared on any page we could open.
- Integration: URA says the development "will be integrated with Bedok South MRT Station, a bus interchange and retail spaces".
- Tender: launched 30 March 2026, closed 15 July 2026, awarded 20 July 2026 to the highest tenderer.
The Master Plan describes the wider Bayshore neighbourhood, next to East Coast Park: its first Build-To-Order and GLS projects were launched in 2024, and URA plans an integrated transport hub, a central park, a school and a transit priority corridor, linked by a community loop. It also describes a new Bayshore SAFRA clubhouse directly connected to Bedok South MRT station and the bus interchange.
Not confirmed on any page we could open: a project name, unit mix, prices, a launch date, or completion dates for the homes, retail space and bus interchange. URA's award release names the two tenderers but not who owns them; we could not open any developer statement, so this page names only what URA published. A station that opens in December does not mean the homes above or beside it are close to completion.

How does Bayshore Drive's land price compare with nearby sites?
URA publishes each award as a price per square metre of GFA. Converted at 10.7639 square feet to the square metre (the factor in our sqm to sqft converter), three east-side awards compare like this, on our arithmetic:
- Bayshore Road, awarded 28 March 2025: residential; S$14,944.52 per square metre of GFA, about S$1,388 per square foot per plot ratio (psf ppr), to Sing-Haiyi Garnet Pte. Ltd. URA had estimated about 515 homes.
- Bayshore Drive, awarded 20 July 2026: commercial and residential; S$14,243.83 per square metre, about S$1,323 psf ppr. URA gives one price for the whole GFA, with no split between homes and shops, so this is a blended rate.
- New Upper Changi Road, awarded 4 September 2026: residential; S$16,544.65 per square metre, about S$1,537 psf ppr, to United Venture Development (Daisy) Pte. Ltd. and CL Sapphire Pte. Ltd. URA describes this site as near Bedok MRT station, an existing station rather than one of the three opening in December, with about 1,010 homes.
Two cautions. Bayshore Drive's blended rate is not like for like with the two purely residential sites. And a land rate is not a selling price: it says nothing about construction costs, margins or what buyers will be quoted. Our comparison of 2026 GLS awards puts these figures among the year's other tenders.
What should a buyer check before relying on "near Bedok South MRT"?
Before paying a booking fee on any east-side project marketed on the new stations, settle these in writing:
- Which station, which exit, how far. No official page we read lists the exits. Walk and time the route after 26 December; a brochure's straight-line distance is not a walking time.
- Integrated or nearby. URA ties integration with Bedok South to the Bayshore Drive development. A project on another plot is, at most, near the station. Our guide to checking new-launch marketing claims covers how to ask for the source of each claim.
- Open now or planned. The three stations have a date. The bus interchange, retail, central park, school and SAFRA clubhouse at Bayshore had no completion date on the pages we read. Check any amendment near your plot with our Master Plan guide.
- What nearby homes actually sold for. Use URA's caveat search for condominiums around Bayshore and Bedok South before judging a price list against a "new MRT" premium.
- Schools and the lease. Check primary-school distances with our school distance guide, and count how many of the 99 years will remain at handover with our lease start date guide.
More site-by-site research is on the research topic page.
Common questions
When does Bedok South MRT station open?
LTA announced on 4 November 2026 that Bedok South, Sungei Bedok and Xilin stations open for passenger service on 26 December 2026.
Is the Bayshore Drive development connected to Bedok South MRT?
URA says the Bayshore Drive development will be integrated with Bedok South MRT station, a bus interchange and retail spaces; no completion date for it appeared on any page we could open.
How many homes will Bayshore Drive have?
URA estimates the site could yield about 1,280 residential units; no final number appeared on any page we could open.
Which new station is an interchange?
Sungei Bedok, where passengers can transfer between the Thomson-East Coast Line and the Downtown Line.
Sources
- Thomson-East Coast Line page lta.gov.sg
- launched the Bayshore Drive tender ura.gov.sg
- awarded Bayshore Drive ura.gov.sg
- announced the opening date lta.gov.sg
- Master Plan 2025 page for the East ura.gov.sg
- current GLS sites page ura.gov.sg
- closed 15 July 2026 ura.gov.sg
- S$14,944.52 per square metre of GFA ura.gov.sg
- about 515 homes ura.gov.sg
- S$16,544.65 per square metre ura.gov.sg
- describes this site ura.gov.sg